‘How’ does the permitting process work?

Step 1
Submission of ‘all’ permit applications must still be presented to Belle Isle City Hall for preliminary review and approval. With few exceptions, there will be a charge to the applicant for this preliminary review through our Zoning Department.

Step 2
Once the City of Belle Isle Zoning has performed a preliminary review of the permit application and found it to be in compliance with City code requirements, the application will receive City approval via a zoning stamp and signoff.

Step 3
The approved/stamped permit application will then be given to the City of Belle Isle Building Inspection Services Consultant which will issue the associated permit and perform any/all required inspections. Inspections can be made from 8:00am-1:00pm Monday-Friday.  It is requested that inspections be scheduled 24 hours in advance via email at bidscheduling@universalengineering.com.

Should you have any questions after reviewing this information, please contact the City Hall staff for assistance 407-851-7730. 

To find out more about the Florida Building Code please go to Floridabuilding.org

To find out more information on CIty Code Ordinances please go to Municode.com

 
Special (After Working Hours) Inspection Fees:
Requests for special after-hours, week-end or holiday inspections must be submitted in writing by the developer/contractor to the Building Department 24hrs in advance of the requested inspection at bidscheduling@universalengineering.com. The minimum number of hours that will be approved is 4-hours per inspector. No inspection(s) will be performed until the assessed fee has been paid. * After the initial 4-hours, an additional fee will be charged. Normal working hours are 8:00am-4:00pm, Monday through Friday.